Chapel Wharf

995 apartments. 4 towers. 22-month programme.
The 56,000m² development delivered 995 apartments across four towers rising to 23 storeys. Its scale provides proven evidence of what a manufacture-led approach can achieve and helped inform the continued evolution of the systemised approach that underpins hyTower today.

Designed for manufacture. Ready to assemble.

More than 8,000 structural elements and 1,450 bathroom pods were manufactured offsite, with structure, façade, balconies and pods coordinated as part of an integrated delivery strategy.

Precast crosswalls, architectural sandwich panels and pre-glazed balcony units increased the amount of work completed in controlled manufacturing environments before components reached site - reducing traditional site activity and creating a more consistent and predictable assembly process.

995

apartments

73

storeys across four towers

4

tower cranes

Proven in Manchester.
Evolved for London. 

Chapel Wharf demonstrated how systemised construction could deliver substantial residential scale with a leaner site operation. Components from five manufacturing locations were coordinated on a just-in-time basis to feed four tower cranes operating simultaneously, while a site team of just 38 people supported delivery across the development.
 

The principles proven at Chapel Wharf - integrated design, large-scale offsite manufacture, repeatable components, coordinated logistics and controlled assembly - have helped shape the continued evolution of hyTower, with the system now being deployed through hyTower London across high-rise residential projects in the capital.

5

manufacturing locations

8,000+

offsite-engineered structural components

38

on-site
staff

“This is a team that are proactive in their approach to safety and that everyone goes home safely. Not only this, but their maturity and commitment shone through by showing great leadership when participating on the Project Safety Leadership Team.

Rohan Evans, Project Director from Sir Robert McAlpine

bottom of page